JDR Wins Equinor Contract for Hywind Tampen Floating Offshore Wind Cables
JDR Cable Systems Ltd.ย has secured a major contract fromย Equinorย to supply subsea cables forย Hywind Tampen, the first floating offshore wind project designed to power oil and gas platforms. This agreement further strengthens JDRโs role in the fastโgrowing floating wind market. In addition, the project showcases how offshore wind can directly reduce emissions from offshore production.
You can learn more about JDR atย https://www.jdrcables.comย and Equinor atย https://www.equinor.com.
Scope of the Hywind Tampen Cable Supply
Under the contract,ย JDRย will supplyย eleven 66 kV dynamic inter-array cables, each aboutย 2.5 kmย long. Furthermore, the company will deliverย two static export cablesย that measure roughlyย 12.9 kmย andย 16 km. Each cable includes a JDRโdesignedย breakaway systemย along with a full range of subsea cable accessories, so the overall system remains safe and reliable during extreme conditions.
The project site lies in theย Tampen area of the North Sea, and JDR plans to complete cable delivery inย 2022.
First Floating Offshore Wind Power for Oil and Gas Platforms
Hywind Tampen will become theย first project worldwideย to power oil and gas platforms withย floating offshore wind technology. Unlike fixedโfoundation wind farms, floating projects bring far more technical challenges and rely on less mature technology. Consequently, subsea cables face high dynamic stress from waves, currents, and continuous platform movement, so they must withstand constant motion over many years.
Because of these demands, JDR designs each cable system for longโterm reliability in harsh offshore environments.
Hywind Tampen Wind Farm Configuration
Theย Hywind Tampenย development will featureย 11 floating wind turbinesย developed byย Equinor. Each turbine will provideย 8 MW, giving the wind farm a total capacity ofย 88 MW. As a result, the project will supply aboutย 35% of the annual power demandย for theย Snorre A and Bย andย Gullfaks A, B, and Cย oil and gas platforms.
Water depths reach aroundย 300 meters, which makes this site much deeper than earlier floating wind projects. Consequently, Hywind Tampen stands out as the first floating wind project built specifically to power offshore oil and gas installations. To handle higher water pressures and demanding seabed conditions, JDR will design the cables that connect the loop to theย Snorre Aย andย Gullfaks Aย platforms with enhanced robustness.
JDR and TFKable Groupโs Dynamic 66 kV Experience
JDR, part of Polandโbasedย TFKable Group, already brings proven experience in this emerging niche. Previously, the company delivered the worldโs first application ofย dynamic 66 kV cable technologyย and aย breakaway systemย to theย WindFloat Atlanticย floating wind farm. This track record gives JDR a strong technical foundation for Hywind Tampen.
For this project,ย TFKableย will manufacture the power cores at itsย Bydgoszcz factory in Poland. After manufacturing, JDR will assemble all subsea cables and accessories at itsย U.K. facilities in Hartlepool. This integrated approach helps ensure consistent engineering, production, and testing from start to finish.
You can learn more about TFKable Group atย https://www.tfkable.com.